|
|
~Preparing the Land for our Cabin~
|
|
Our big purchase...a five acre
slice of Alaska with a million dollar view. |
|
April
18th-19th, 2004
Lots of snow still,
up to the knees, but after cutting some trees down we found some dry land to
walk on. The future cabin site. |
|
April 28-29th
After moving the logs we cut, we
made sure they were off the ground and started peeling. The bark was
still tight to the trunk, so the first weekend of peeling only produced 5
peeled logs.
|
|
May 4 - 5th
A bunch of new logs for me to peel. Luckily these ones started peeling
without much use of the drawknife. |
|
May 9-10th
Snowing and 32 degrees...what a way to start working.
Burnt lots of limbs from nearby slash pile. Warmed up to 55 that day.
Peeled 16 logs this weekend. |
|
May 15th
Hiked into our moose lake to get the
60+ moose rack out we found the year earlier. I ended up hiking 7
miles in socks due to open blisters on both heels. The rack is a
special addition for our cabin. |
|
May 16-17th
Aaron come-alongs log that is too heavy for us to
carry. We did eventually carry it the last little bit.
After moving 7 logs the first morning I had my work
cut out for me to peel. Peeled 7 the first day. |
|
Nice pile accumulating of peeled logs.
For the whole weekend we moved 13 logs out of the woods and I peeled 15
logs.
Kodi taking a snooze out of the sun,
behind our big log |
|
May 23 - 24th
Moved 10 more logs out of woods and
peeled all ten on the first day. Worked until 10:00- sunset now around 1130.
My peeling site. |
|
After two days of A LOT of wind this
is what I look like. The second day I peeled 5 large logs and 3 gable
logs. This weekend marked us at 60 logs cut, 58 peeled. |
|
May 30-31st
Not a very successful weekend Only peeled 6 and cut 8
logs. Hauled 8 - 80# bags of concrete |
|
June 6 - 7th
Bug season in Alaska, and it is only
the start. Mosquitoes are out 24 hours a day in full force.
Digging our post holes. Finished cutting 7 logs and
peeling 9 logs= 75 total cut and peeled. |
|
Digging second post hole on first
day. Kodi escaped mosquitoes by being buried in the dirt, it also kept in
cool on a fairly hot and humid day. |
|
Finished weekend with all 8 post
holes dug about 4 feet deep. Plan for 14X18 cabin. Hauled in 6 more 80# bags of
concrete. |
|
June 13
- 14th Hammering in log posts to set up
string to square and level site. Hiked in 10, 80# bags of concrete.
Yes, even I know how to level. |
|
Set up string level, and squared work
site. Pounded steel rods into post holes in place of rebar.
First three concrete posts done .
|
|
Visiting moose in morning.
Finished 7 out of 8 posts, only 1
more six inch post to poor = only two more bags of concrete. |
|
June 20-21 Our first log, half logs on both short
ends of the cabin.
Aaron's
homemade scribe, learning to scribe on our first whole log. |
|
Sawing the round notch after scribing.
Hauling our center log to the cabin site. This
is our homemade system to move logs. |
|
Chiseling just one of many to come
round notches. |
|
Aaron's large round notch.
Getting the floor joists started. |
|
June 27-28th
The outhouse hole finally dug, about five feet deep.
The rocks are part of our foundation around the base to make it level and
stronger.
|
|
July 18-19th Aaron and Adam hauled 70- 2X6s and 9
sheets of plywood the 500yards to our cabin site, it took 9 trips in all.
Adam and Aaron scrubbing some mold off the logs that
were close to the ground. |
|
Adam and Aaron sawing notches. We got four
logs up this first weekend back from our vacation. We still have a lot
to learn about scribing and notching.
More chiseling. |
|
Started the floor boards. Adam wasn't
very happy with the way the screw driver was working.
Somehow the drill kept spinning off the screw making lots of little
holes in our floor boards!!! |
|
|
|
|
|
|
|